Gordon
Persons State Office Building - Montgomery, Ala.
Plumbing
and HVAC systems were installed by Hardy in this 600,000 S.F. state government
office building. Equipment included two (2) centrifugal chillers totaling
1,650 tons, two (2) steam boilers, 10 pumps, 35 air handling units, 780
variable air volume (VAV) zones, and direct digital temperature controls.
Plumbing included water and sanitary sewer systems, and storm water drainage.

Grandview II Office Building - Birmingham, Ala.
This 147,000 S.F. six - floor facility included two (2) screw chillers
totaling 425 tons and various tenant build-outs by Hardy.
Daniel Building
(Compass Bank Headquarters) - Birmingham, Ala.
HVAC and plumbing systems were originally installed by Hardy in this 318,800
S.F. 19-story office building. Renovation of all mechanical systems including
installation of 450-ton chiller by Hardy in 1992 for conversion from multi-tenant
offices to bank headquarters.
Southern
Progress Corporation (division of Time Warner) - Birmingham, Ala.
This publisher of Southern Living magazine and Oxmoor House books has
relied on Hardy since 1988 for the installation and servicing of its mechanical
systems. Building #1: 136,000 S.F., five-story, two (2) 200-ton chillers.
Building #2: 80,000 S.F., three-story, one (1) 240-ton chiller. Media
Services Building: 62,000 S.F., two-story one (1) 175-ton chiller.

Compass Bank Data Processing Center and Harry Brock Public Building -
Birmingham, Ala.
Three floors, 308,000 S.F. Mechanical system installed by Hardy includes
two (2) 267-ton chillers and 12 computer room air conditioning units.
Hardy has also completed the renovation of the new 80,000 S.F. Compass
Bank Operations facility in Homewood, Ala. including 246-tons of air conditioning.

Federal Courthouse - Shreveport, LA
Design-build project for U.S. General Services Administration including
three (3) chillers totaling 900 tons, gas boilers, and variable-air-volume
air distribution system.
SouthTrust
Bank Headquarters and Operations Center - Birmingham, Ala.
This two (2) phase , six-story, 408,000 S.F. project included HVAC and
plumbing systems installed by Hardy. Plumbing scope included water, sanitary,
and storm water piping. HVAC scope included three (3) 450-ton centrifugal
chillers, two (2) 300-ton rotary chillers, five (5) cooling towers, eight
(8) VAV air handling units, roof top units, supply and exhaust fans, steam
humidification, 20 computer room units, and direct digital temperature
controls.

University Park Building 600 (Lakeshore Blvd.) -
Birmingham, Ala.
Hardy installed 400-tons of air conditioning including five (5) water-cooled
package units, two (2) cooling towers, six (6) pumps, one (1) heat exchanger,
30 PIU/variable air volume boxes, and direct digital controls.
|
 |