University
of Alabama at Birmingham - Central Utilities Plant #1
Hardy was prime contractor for this chilled water plant upgrade including
mechanical, electrical, and structural modifications. Phase I: Replace
four (4) 1,000-ton centrifugal chillers with two (2) 2,000-ton chillers.
Phase II: Replace existing 4,500-ton chiller with new 4,000-ton chiller.
AmSouth/Harbert
Plaza - Birmingham, Ala.
Hardy installed the central plant serving downtown office tower with two
(2) 750-ton centrifugal chillers and gas boilers.
Brookwood Medical Center - Birmingham, Ala.
Since 1996, Hardy has performed multiple HVAC renovations, additions,
and equipment replacements worth over $4 million. Projects included replacing
four (4) centrifugal chillers totaling 2,500 tons. 
Baptist Medical
Center, Princeton
- Birmingham, Ala.
Central plant
HVAC equipment installed by Hardy Corporation included two (2) centrifugal
chillers, three (3) boilers, six (6) pumps, and gas and fuel oil piping.
Plumbing system included water and sanitary sewer system, and storm water
drainage.

State Farm Regional Headquarters - Birmingham,
Ala.
Hardy installed HVAC and plumbing for State Farm's new Alabama-Mississippi
regional headquarters including 1,575-tons of cooling. Phase II (adding
50,000 S.F.) included mechanical additions and renovations.
Metro
Center Mall - Jackson, Miss.
Hardy replaced two (2) 550-ton centrifugal chillers, two (2) cooling towers,
and re-worked the chilled water pumps in the renovation of this physical
plant.

Dillards Department Stores (formerly Gayfers)
Chiller replacements for 25 stores in AL, GA, FL, KS, KY, MS, MO, MT,
ND, OH, SC, and TN. Stores continued uninterrupted retail operation during
Hardy's work.
|
 |